Capital Projects Dashboard - Citywide Budget and Schedule

Mayor's Office of Operationsfb86-vt7uCity Government

All major capital infrastructure projects with a committed budget. Financial information and agency schedule details for each project are joined via FMS ID. Only projects in the design phase or later have project schedules displayed. This dataset is part of the Capital Projects Dashboard. Note: Each row is uniquely identified by its Financial Management Service (FMS) ID. FMS ID is the unique ID that OMB uses for the FMS (Financial Information System). This ID can be universally joined with any OMB dataset that has the same field. The Capital Projects Dashboard is the result of joining OMB’s fiscal data with the agency’s schedule data. FMS IDs and agency projects don't always have a one-to-one relationship (i.e., one project schedule may correlate to multiple FMS IDs, and one FMS may correct to multiple projects with different schedules).

Open at the source

Open in the graph · Relate this dataset · What these columns mean

Freshness

The publisher's promise

How the agency that publishes this data says it keeps the data current.

New

Says it updates
Other
Actually updates about every
—
Publisher last updated the data
Jul 15, 2026

Our mirror

Whether our copy of this data is current with the source.

In sync

We last synced
Jul 15, 2026, 1:26 PM
Rows in our copy
56,525
Rows at the source
56,525
Our copy trails the source by
under a minute

Columns

Each source column, with the name and type we use to store it.

Open the data dictionary

0 of 27 columns carry a concept; 27 carry a description from the publisher. Read the concept column before you join. A column with no concept carries no claim from us, and a name that looks like a key is not one.

Each source column, with the name and type we use to store it.
Source fieldDisplay nameWhat the publisher says it isConceptSource typeStored asStored typeRow identifierUnit
actual_design_start
Actual Design Start
The date when the design phase started (when the project started/became active)
Not bound
Calendar date
actual_design_start
timestamp
empty
fms_project_name
FMS Project Name
The name of the project in the Financial Management System (FMS)
Not bound
Text
fms_project_name
text
empty
sponsor_agency
Sponsor Agency
Common acronym of the city agency that the capital project is being managed on behalf of. This value is derived from the three digit sponsor agency code. May include multiple agencies.
Not bound
Text
sponsor_agency
text
empty
forecast_completion
Forecast Completion
The date when the entire project is expected to be completed
Not bound
Calendar date
forecast_completion
timestamp
empty
agency_data_date
Agency Data Date
The date agency data was updated
Not bound
Calendar date
agency_data_date
timestamp
empty
agency_project_description
Agency Project Description
The short description of the capital project as described by the Sponsor Agency
Not bound
Text
agency_project_description
text
empty
actual_construction_end
Actual Construction End
The date when the construction phase was completed
Not bound
Calendar date
actual_construction_end
timestamp
empty
total_budget
Total Budget
The total cost of the project, as reflected by "Commitments" in the City's Financial Management System (FMS)
Not bound
Number
total_budget
numeric
empty
managing_agency
Managing Agency
Common acronym of the city agency that is responsible for managing the construction and delivery of the capital project. This value is derived from the three digit managing agency code.
Not bound
Text
managing_agency
text
empty
ten_year_plan_category
Ten Year Plan Category
Categories of work as described in city's Ten-Year Capital Strategy
Not bound
Text
ten_year_plan_category
text
empty
community_board
Community Board
Community Board where the capital project is located
Not bound
Text
community_board
text
empty
reporting_period
Reporting Period
The year and the month the report is published (format YYYYMM). The dataset is updated 3 times a year following OMB’s commitment plan release date in Jan/May/Sep.
Not bound
Text
reporting_period
text
empty
agency_project_name
Agency Project Name
The name of the project in the managing agency's project management system
Not bound
Text
agency_project_name
text
empty
actual_construction_start
Actual Construction Start
The date when the construction phase started
Not bound
Calendar date
actual_construction_start
timestamp
empty
spend_to_date_1
Spend to Date (%)
The amount of money spent to date, as reflected by "Liquidations" in the City's Financial Management System (FMS) shown as a percentage of Total Budget (%).
Not bound
Number
spend_to_date_1
numeric
empty
forecast_current_phase_end
Forecast Current Phase End
The date when the current phase of the project is expected to be completed
Not bound
Calendar date
forecast_current_phase_end
timestamp
empty
actual_design_end
Actual Design End
The date when the design phase was completed
Not bound
Calendar date
actual_design_end
timestamp
empty
current_phase_start
Current Phase Start
The date when the current phase of the project began
Not bound
Calendar date
current_phase_start
timestamp
empty
current_phase
Current Phase
The phase the project is in
Not bound
Text
current_phase
text
empty
fms_data_date
FMS Data Date
The date FMS data was updated
Not bound
Calendar date
fms_data_date
timestamp
empty
fms_id
FMS ID
Unique identifier in the Financial Management System (FMS)
Not bound
Text
fms_id
text
empty
spend_to_date
Spend to Date
The amount of money spent to date, as reflected by "Liquidations" in the City's Financial Management System (FMS)
Not bound
Number
spend_to_date
numeric
empty
actual_construction
Actual Construction Procurement Start
The date when the construction procurement phase started
Not bound
Calendar date
actual_construction
timestamp
empty
pid
PID
Unique identifier that represent a set of schedule managed by agency.
Not bound
Number
pid
numeric
empty
borough
Borough
Borough (Bronx, Brooklyn, Manhattan, Queens, Staten Island)
Not bound
Text
borough
text
empty
budget_line
Budget Line
Capital budget unit of appropriation
Not bound
Text
budget_line
text
empty
actual_construction_1
Actual Construction Procurement End
The date when the construction procurement phase was completed
Not bound
Calendar date
actual_construction_1
timestamp
empty

Download

This file was produced on Aug 25, 2026, 10:10 PM.

Use the API

These are the exact calls for this dataset, against the host you are reading this on. Each one answers JSON, needs no key, and is rate-limited.

Canonical metadata, both freshness axes, columns, attribution, lineage.

curl https://citytap-web-citytap-prod.codenow.nyc/api/datasets/fb86-vt7u

Ranked, dimension-tag-confirmed relatives of one dataset.

curl https://citytap-web-citytap-prod.codenow.nyc/api/datasets/fb86-vt7u/partners

Up to 50 distinct sample values of one named column. Not a raw-rows dump.

curl 'https://citytap-web-citytap-prod.codenow.nyc/api/rows/fb86-vt7u?column=actual_design_start'

A CSV sample of up to 1,000 rows, honest about being a sample.

curl https://citytap-web-citytap-prod.codenow.nyc/api/export/fb86-vt7u/csv

Redirect to the dataset's newest curated parquet object.

curl https://citytap-web-citytap-prod.codenow.nyc/api/export/fb86-vt7u

Known defect: the presigned URL currently resolves only inside the cluster. Use the /csv sibling until the presign is public.

Refresh this dataset

600 refresh slots are open this hour. Anyone can use them — no account needed.

Source and attribution

Where this data comes from, which version we hold, and what we changed.

Source
https://data.cityofnewyork.us/d/fb86-vt7u
Version
Content hash: ddaea1060f665a1cdf96c2d259b77c5402859d85cf22922cc041d0d01eeeeb5a
What we changed
We did not change the data. We stored it as published.
Publisher
codenownyc
We retrieved it
Jul 15, 2026, 1:26 PM

Update history

Update history
StartedKindResultRows writtenProduced by
Aug 25, 2026, 6:15 AMfull_replacesuccess56,525